A project is notifiable if
either of these tests is met:
✕Test 1: more than 30 working days and more than 20 workers working simultaneously at any point.
✕Test 2: more than 500 person-days of construction work.
Person-days: this calculator estimates person-days as working days × average workers per day. If the workforce changes significantly during the project, use a more accurate total rather than relying on a simple average.
Important: F10 notification is only one CDM duty. A project can still be subject to CDM requirements even where notification is not required.
Use as a sense-check: confirm the project details and dutyholder arrangements before relying on the result. Where a project is notifiable, the client has the notification duty under CDM 2015.